Design Approval (Land Sublease)

 

Soil Investigation
After Reservation Agreement is signed, Locator may apply “Application for Soil Investigation” with Format A-1 if locator requires it for their reference.

Survey Work
After Land Sublease Agreement is signed, Locator may apply to MJTD for the “Application for Survey Work Format A-1".

Temporary Works (if any)
After Land Sublease Agreement is signed, Locators may apply temporary work by submitting a “Temporary Preparation Works Application (Format A-2)”. "Temporary Work" is for site preparation work only. Locator may start Foundation work and other permanent works after getting approval of Start of Construction from MJTD.

Design Approval Application (DAA)
After signing the “Land Sublease Agreement” and full payment to MJTD, Locators shall submit the “Design Approval Application” with Format A_C. MJTD will officially accept with 3 sets of hard and soft copies (CD) all of the require document can be completed according to Exhibit 2 of Industrial Zone, Internal Regulations.
Note: Locator shall receive approval of MJTD and relevant Authority.

Design Change (if any)
When there is design changes/modification during construction stage or after completion stage, Locators may apply the "Design Change/Design Modification Application" with Format E_C. Locators cannot start the design change work until getting the approval of Design Change from MJTD.