Start of Construction

Start of Construction
After the Building Permit and Fire Safety approval is approved by TSMC, Locators may apply the Application for "Start of Construction" document with Format B to MJTD.

Piling Work (if any)
After Design Approval Application is approved by MJTD and Permit of Temporary Commencement of Building/Factory Construction Work is approved by TSMC, Locators may apply “Start of Construction (Piling Works Only) Application” with Format B-1. Locator cannot start other construction works until getting approval of Start of Construction from MJTD.

Permanent Fencing Work (if any)
After Design Approval Application is approved by MJTD, Locators may apply "Start of Construction (Permanent Fencing Works Only) Application" with Format B-2. Locators cannot start other construction works until getting approval of Start of Construction from MJTD.

Removal of Earth from the Lot
Locators may apply the "Removal of Earth from the Lot with Format D" 45 days in advance and shall comply Articles 17 of Rules of Construction.